QIC Forest Lake

A megawatt-scale shopping centre installation.

Forest Lake, QLD

An expansive rooftop solar system at Forest Lake Shopping Centre, completed in 2023.

System capacity

Forest Lake Shopping Centre.

Annual production

Reported.

Performance ratio

Reported.

PROJECT OVERVIEW

Forest Lake’s rooftop becomes an energy asset.

The installation of an expansive 1003.92kW solar system on Forest Lake Shopping Centre, completed by DS Energy in 2023.

The installation of an expansive 1003.92kW solar system on Forest Lake Shopping Centre, completed by DS Energy in 2023.

The installation is comprised of 2136 Astronergy CHSM60N(DG)/F-HC-470w panels. It’s annual production is 1.563 GWh with a performance ratio of 81.3%

The installation is comprised of 2136 Astronergy CHSM60N(DG)/F-HC-470w panels. It’s annual production is 1.563 GWh with a performance ratio of 81.3%

CLIENT

QIC Forest Lake

COMMISSIONED

2023

01 / THE CHALLENGES

The project context.

The project context.

The project involved installing a large solar array on an active shopping centre.

Retail scale

The system is reported at 1,003.92 kW.

Extensive rooftop

The installation comprises more than 2,100 modules.

THE SYSTEM AT WORK

From site to useful energy

Site assessment

Converts sunlight into clean electricity.

Tailored design

Upgraded infrastructure moves energy safely across the site.

Delivery and care

On-site generation helps reduce reliance on the grid.

02 / THE SOLUTION

More than 2,100 modules installed.

More than 2,100 modules installed.

The installation is comprised of 2136 Astronergy CHSM60N(DG)/F-HC-470w panels. It’s annual production is 1.563 GWh with a performance ratio of 81.3%

Capacity

1,003.92 kW

Modules

2,136 Astronergy 470 W panels

Completion

2023

DS Energy completed the rooftop installation in 2023.

03 / THE RESULTS

1.563 GWh of annual generation.

1.563 GWh of annual generation.

The installation is comprised of 2136 Astronergy CHSM60N(DG)/F-HC-470w panels. It’s annual production is 1.563 GWh with a performance ratio of 81.3%

Annual production

Reported project figure.

Reported project figure.

Performance ratio

Reported project figure.

Reported project figure.

System capacity

Retail rooftop installation.

Retail rooftop installation.

On-site generation

The shopping centre roof supplies renewable electricity.

Reported performance

The case study reports an 81.3% performance ratio.

Thinking at megawatt scale?

Let’s assess your site and design around its operating needs.

Create a free website with Framer, the website builder loved by startups, designers and agencies.